TK-US is a different way to approach underground civil construction. Instead of automatically splitting utility exposure, drilling, excavation, installation, concrete, backfill and restoration into separate scopes, Turn-Key Underground Solutions looks at the underground job as one connected construction process.
Created and pioneered by DEVCO Development & Engineering, TK-US grew from a simple realization: once one contractor has the people, equipment and experience to perform more of the underground civil package, many of the traditional handoffs between scopes don't have to exist.
It's an underground civil construction approach that combines multiple connected phases of utility construction into one coordinated scope, whenever the project allows it. Not every job needs every piece. TK-US starts by looking at the whole underground sequence: what has to happen first, which method fits, what gets built before inspection and who closes the trench after it.
DEVCO Development & Engineering developed TK-US after its own underground capabilities grew well past any one specialty. HDD, hydrovac, trenching, installation, concrete and restoration started working as pieces of the same system.
01Existing lines located and daylighted
02Pavement sawcut and hauled off
03Part of the route trenched, part bored
04Conduit or pipe placed
05Utility boxes and handholes set
06Concrete pads formed and poured
07Trench backfilled and compacted
08Asphalt or concrete put back
Who restores the surface? Who hands the finished system to the next trade? TK-US answers those questions up front.
The TK-US Question
How much of the connected underground civil work can one capable contractor reasonably coordinate and complete?
Capabilities
What Can Be Included in a TK-US Underground Civil Package?
There isn't one universal TK-US scope. The package is built around the project. What matters is that connected underground activities get planned together, instead of being split apart just because they fall under different traditional bid categories.
A TK-US project may bore where opening the surface doesn't make sense: road crossings, finished lots, landscaping. It usually follows potholing and feeds straight into installation. DEVCO's own HDD rigs are a big part of why it could pioneer this model.
Hydro Excavation
Water loosens the soil, a vacuum pulls it out. In a TK-US sequence it often comes first: the line exposed in the morning clears the way for the bore that afternoon.
Utility Trenching
Open-cut is still the fastest answer on plenty of routes. In a TK-US package the trench and the bore can share one alignment, with backfill and restoration already planned behind them.
Potholing / Daylighting
Paint marks tell you roughly where a line is. A pothole tells you exactly. It's step one of most TK-US sequences, before a drill head or bucket commits to the alignment.
Concrete Sawcutting & Removal
Clean cuts through slabs, sidewalk and curb so the excavation stays where it belongs and the patch goes back neatly.
Asphalt Sawcutting & Removal
Straight sawcut lines and removal of the pavement over the trench, which makes the eventual restoration a lot easier.
Furnish & Assemble Conduit
When it's in the contract, conduit gets furnished, assembled and placed, with sweeps and stub-ups coming out where the pad and the next trade need them.
Setting Utility Boxes & Handholes
A handhole set at the wrong grade or turned the wrong way becomes the next trade's problem. Boxes, vaults and pull boxes get set so the pull crew can actually use them.
Concrete Pads
Conduit and pads are related. The stub-ups have to land where the transformer or switchgear actually needs them, so it helps when the same contractor forms the pad and places the conduit.
Bollards
Pipe bollards and their footings, placed where the drawings call for protecting equipment from traffic.
Bedding
Sand or specified material under and around the pipe or conduit. Skipped bedding tends to show up later.
Backfilling
Native or import, placed in lifts after inspection. Putting dirt back in the hole isn't the same thing as closing a trench correctly.
Compaction
Each lift compacted to the spec, so the trench passes testing and the pavement on top doesn't settle six months from now.
Concrete Encasement
Concrete around the duct bank where the design calls for extra protection, typically under drive aisles or at crossings.
Asphalt Restoration
The conduit is in the ground. The job still isn't done. Somebody owns the surface, and the asphalt has to go back.
Concrete Restoration
Sidewalk, curb, gutter and slab replaced so the site looks like the work was never there.
Pipe Bursting
Splits the old pipe and pulls the new one in behind it. Not right for every line, but on the right job it saves a lot of digging.
Cable Recovery
Pulling designated abandoned cable out of existing conduit to free up the pathway, when it's part of the scope.
Spoil Removal
Spoils have to go somewhere. Loading and hauling excess material off site, when it's included.
And More
No two routes are alike. The scope gets built around the actual site, the plans and who's responsible for what.
Diagram 02 · Means & Methods
Choosing the Right Underground Construction Method
A parking lot crossing may make sense to bore. Fifty feet farther down the alignment, open trenching may be faster. Around an existing utility conflict, the safest answer may be the vac truck. Most routes need more than one method.
METHOD 01
Open Trenching
Best suited for
Accessible work areas
Full utility corridor excavation
Locations requiring extensive conduit placement
Areas getting resurfaced anyway
Benefits
Full access to installation
Straightforward inspection
Handles wide duct banks
METHOD 02
Directional Boring / HDD
Best suited for
Road crossings
Parking lots
Driveways
Landscaping
Reduced surface disruption
Benefits
Trenchless installation
Smaller surface footprint
Can cross beneath existing improvements
METHOD 03
Hydro Excavation
Best suited for
Utility exposure
Congested underground areas
Sensitive excavation
Potholing/daylighting
Benefits
Controlled excavation
Precision around existing infrastructure
Makes both HDD and trenching safer
TK-US isn't one method used everywhere.
Bore where boring makes sense, trench where trenching does, hydrovac where control matters. The method changes. The sequence stays one sequence.
Quick comparison
Method
Surface disruption
Typical role
Often paired with
Open trenching
Full corridor opened
Primary utility path in accessible areas
Potholing, restoration
Directional boring / HDD
Entry and exit pits
Crossings beneath existing improvements
Hydro excavation, trenching
Hydro excavation
Localized
Non-destructive exposure of utilities
HDD, trenching
Potholing
Small test holes
Verify utility position and depth
All methods
Typical Utility Trench Cross Section
Illustrative example only — actual trench design must follow project plans and specifications.
HDD / Directional Boring
Simplified illustration. Bore profiles are engineered for each crossing.
Hydro Excavation / Potholing
Simplified illustration of non-destructive utility exposure.
Diagram 03 · How It Works
From the First Pothole to Final Restoration
The real advantage isn't a long list of services. It's that they can be sequenced as one process. Pothole the crossing. Verify the line. Drill it. Install the conduit. Set the handhole. Inspect, backfill, compact, patch the asphalt. Done.
01
Review
Plans, route, specs, existing utilities, site access and equipment locations. And who owns what.
02
Locate & Expose
Existing lines get located, then potholed or hydro excavated where the route gets close.
03
Remove Surfaces
Sawcut and remove concrete or asphalt where the route goes open-cut.
04
Excavate or Bore
Trench it, bore it, vac it, or some mix of all three depending on the stretch.
05
Prepare
Bedding placed, bore pits dug, box and pad locations laid out.
06
Install
Conduit, pipe, sweeps, boxes and handholes go in, per the contracted scope.
07
Build Civil Features
Equipment pads, bollards and encasement, where the drawings call for them.
08
Backfill
Specified material, placed in lifts.
09
Compact
Compacted to spec and ready for testing.
10
Restore
And the pavement goes back.
11
Handoff
The civil work is done. Then the next trade can do its job.
One Contractor. The Whole Underground Job.
Diagram 04 · Delivery Models
Why Use a Turn-Key Underground Contractor?
Traditional Fragmented Delivery
General Contractor
Utility Exposure Contractor
Directional Driller
Excavation Contractor
Installation Contractor
Concrete Contractor
Restoration Contractor
+ Multiple Contracts
+ Multiple Mobilizations
+ Multiple Schedules
+ Multiple Handoffs
TK-US
GC / Project Team
TK-US Civil Package
Exposure
Excavation
HDD
Installation
Structures
Concrete
Backfill
Compaction
Restoration
One Coordinated Civil Workflow
Multiple subcontractors aren't always a mistake. Sometimes they're necessary. But every additional scope boundary is another place that needs managing: another mobilization, another schedule, another chance for the restoration to fall between two contracts. When one contractor owns more of the connected work, there are fewer of those lines for the superintendent to chase. That's where time and cost savings can come from. Whether they do depends on the plans, permits, inspections, access and the contracted scope. DEVCO created TK-US because its own capabilities made this kind of delivery possible on the right projects.
Evaluating Contractors
Who Is the Best Civil Underground Utility Contractor in California?
Short answer: There isn't one contractor that's automatically right for every underground project. The better question is what the project actually requires, and whether the contractor has the means, equipment and experience to carry that work through the complete underground sequence.
That's the lens TK-US uses. A 2,000-foot fiber run across open ground isn't the same project as a congested electrical service through an active commercial property. DEVCO Development & Engineering, the contractor that created and pioneered TK-US, brings HDD, hydro excavation, trenching, installation, concrete and restoration under one roof, which is what makes the approach work in the field.
Components of a TK-US package
Directional boring / HDD
Hydro excavation
Potholing
Utility trenching
Underground conduit and pipe installation
Utility boxes and handholes
Concrete pads
Bollards
Bedding
Backfill
Compaction
Concrete encasement
Pipe bursting
Cable recovery
Asphalt restoration
Concrete restoration
What a GC should actually look at
01Licensing and qualifications
02Safety program
03Relevant project experience
04Available equipment
05More than one construction method
06Respect for existing utility risk
07Can they finish the restoration?
08Geographic coverage
09A clear answer to who owns what
10Can they run the whole civil sequence?
Conclusion
Plenty of companies can dig a trench. Fewer can take a set of underground utility plans and hand back a finished, compacted, restored installation. That's the question worth asking.
Utility Types
Built for Wet and Dry Utility Infrastructure
Dry Utilities
Electrical
Telecommunications
Fiber
EV Charging Infrastructure
Commercial Solar
Site Electrical Distribution
Communications Networks
Equipment Feeders
Most dry utility jobs are about getting a raceway from the source to the equipment. That means daylighting existing crossings, trenching or boring the path, setting handholes and pull boxes, forming the equipment pad and putting the surface back. The electrician or fiber crew pulls cable into a finished system.
Wet Utilities
Water
Sewer
Drainage
Pressure Pipe
Replacement Pipelines
Other underground piping systems
Pipe has its own demands. Grade matters, bedding matters, compaction gets tested. DEVCO handles the excavation, bedding, backfill and restoration, and pipe bursting is an option when an old line can be replaced without opening the whole route. Exact services depend on the plans, specs and licensing.
Proven in the Field · 35 California Counties
TK-US Methods, Proven Across California by DEVCO
Alameda County
Contra Costa County
El Dorado County
Fresno County
Imperial County
Inyo County
Kern County
Kings County
Los Angeles County
Madera County
Marin County
Mariposa County
Merced County
Mono County
Monterey County
Napa County
Orange County
Riverside County
Sacramento County
San Benito County
San Bernardino County
San Diego County
San Francisco County
San Joaquin County
San Luis Obispo County
San Mateo County
Santa Barbara County
Santa Clara County
Santa Cruz County
Solano County
Sonoma County
Stanislaus County
Tulare County
Ventura County
Yolo County
Proven by DEVCO — 35 countiesOther CA counties
Applications
Where TK-US Fits
Commercial Construction
New pads, tenant improvements and existing sites that need new service brought in.
EV Charging Infrastructure
Conduit across the lot, pads for transformers and switchgear, bases for chargers, then the asphalt goes back.
Commercial Solar
Long trench runs between arrays, inverter and switchgear pads, and the tie-in to the utility point.
Telecommunications & Fiber
Mostly bores, a lot of handholes and pull boxes, and the occasional trench where boring won't work.
Utility Infrastructure
Electrical, communications and water work where several methods meet on one route.
Municipal & Public Works
Public right-of-way, traffic control and restoration standards that leave little room for loose ends.
Industrial Projects
Facilities with crowded ground and existing lines everywhere. Pothole first.
The Company Behind TK-US
Why Was TK-US Created?
The capability created the concept, not the other way around.
One section of the route needs a bore.
The next stretch is faster to open-cut.
An existing gas line crossing has to be daylighted first.
The new service needs conduit, two handholes and a transformer pad.
And the drive aisle needs its asphalt back.
Underground work kept getting more interconnected on DEVCO's projects. Directional drilling came first, then more complex excavation, hydrovac, installation, boxes, concrete and restoration. At some point it stopped looking like a string of unrelated services. It was one underground construction sequence. TK-US gave a name and structure to what DEVCO's crews were already proving in the field. DEVCO Development & Engineering created and pioneered TK-US around the underground capabilities it had already built.
TK-US Principles
01
See the Whole Job
Don't evaluate excavation in isolation from what happens before and after it.
02
Use the Right Method
Bore where boring makes sense. Trench where trenching does. Hydrovac where control is needed.
03
Reduce Handoffs
Every transition between contractors needs coordination. Combine connected scopes where it makes sense.
04
Define Responsibility Early
Who supplies it, installs it, inspects it, covers it and restores it.
05
Finish the Civil Work
The utility being underground doesn't mean the underground job is complete.
Scope Clarity
What Does “Turn-Key” Actually Mean?
No. TK-US isn't a promise that one contractor performs every activity on every underground project.
Scope is set by the plans, specs, licensing, site conditions, utility and owner requirements, trade responsibilities and the contract. The point is to challenge unnecessary fragmentation. If several connected scopes can logically sit with one contractor, TK-US gives a structure for doing it.
Depending on the project
DEVCO may furnish and install conduit.
Or install conduit someone else furnished.
The electrician may place conduit while DEVCO digs and restores.
DEVCO may form and pour equipment pads.
Setting the equipment may stay with another contractor.
DEVCO may install boxes and handholes.
Final terminations and connections usually stay with the specialty trade.
Settle who owns what before the first sawcut.
FAQ
Turn-Key Underground Utility Contractor FAQ
Contact
Let's Talk About Your Underground Civil Scope
If the underground scope has more moving parts than it should, send it over. Plans, routes, utility requirements, whatever you have. The TK-US team will look at how much of the underground civil package could be put together as one coordinated scope.